| Document number | DTL-PRJ0072-ITP-001 |
| Revision | A — Issued for Approval |
| Date | 16 July 2026 |
| Parent | DTL-PRJ0072-QMP-001 Quality Management Plan, Section 4 |
| Standards | AS/NZS 4130 · approved fusion parameters (DTL-HDPE-TEM-0003) |
| Attention | Mr John Stephens — Principal Representative |
| No. | Activity | Acceptance criteria | Reference | Record | DTL H/W | SBR H/W | Signed / date |
|---|---|---|---|---|---|---|---|
| 1.0 | Material receival & storage | REF | |||||
| 1.1 | Delivery inspection | Pipe/fittings free of transit damage, gouges >10% wall, UV degradation. | AS/NZS 4130 | Receival log | H | ||
| 1.2 | Certification check | CoC & AS/NZS 4130 compliance certificate present; batch/heat recorded. | SOW MDR | Traceability record | H | ||
| 1.3 | Storage | Supported, shaded, no point loads; UV protection if >12 months. | Mfr guidance | — | W | ||
| 2.0 | Butt fusion jointing | REF | |||||
| 2.1 | Machine set-up | Correct clamps/inserts; faces aligned; drag pressure recorded. | AS/NZS 4130 App. | Weld register | W | ||
| 2.2 | Heater plate temp | Plate temperature within approved range, verified each shift. | TEM-0003 | Heater Plate Check | H | ||
| 2.3 | Fusion parameters | Heat-soak, fusion & cooling times/pressures to approved parameters for size/class. | TEM-0003 | Weld register | H | ||
| 2.4 | Bead inspection | Twin uniform beads, correct width, no mismatch >10% wall; cooled undisturbed. | AS/NZS 4130 | Weld register | H | ||
| 2.5 | Weld numbering | Each joint numbered and located on the weld map. | QMP §5 | Weld map | R | ||
| 3.0 | Installation | REF | |||||
| 3.1 | Stringing & alignment | Route, bend radius ≥ mfr minimum, no kinks; support. | Drawing | ITP sign-off | W | ||
| 3.2 | Road crossings / cover | Depth, sleeve/casing and cover to drawing. | Drawing | ITP sign-off | H | ||
| 3.3 | Earth mounding | Profile and compaction to drawing. | Drawing | ITP sign-off | W | ||
| 4.0 | Connections | REF | |||||
| 4.1 | Flanged / mechanical joints | Alignment, gasket, bolt torque to spec; connection recorded. | Mfr spec | Connection record | H | ||
| 4.2 | ARV, tie-ins, standpipes, scour | Fit, orientation, function to drawing. | Drawing | ITP sign-off | W | ||
| 5.0 | Testing & handover | REF | |||||
| 5.1 | Pressure / leak test | Test pressure, hold time and acceptance to approved test procedure. | AS/NZS 4130 / spec | Test certificate | H | ||
| 5.2 | Weld map complete | All welds mapped and cross-referenced to the register. | QMP §5 | Weld map | H | ||
| 5.3 | Records & MDR | All ITP points signed, NCRs closed, MDR compiled. | SOW MDR | MDR | H |