Prepared for
Shark Bay Resources Pty Ltd
Useless Loop · Heirisson Prong · Shark Bay, Western Australia
Project
Bitterns Recycling — Field Piping Installation
QUALITY — AS/NZS 4130

HDPE Pipeline
Inspection & Test Plan

Document numberDTL-PRJ0072-ITP-001
RevisionA — Issued for Approval
Date16 July 2026
ParentDTL-PRJ0072-QMP-001 Quality Management Plan, Section 4
StandardsAS/NZS 4130 · approved fusion parameters (DTL-HDPE-TEM-0003)
AttentionMr John Stephens — Principal Representative
DRAFT for engineering & SBR review. Hold and witness points and acceptance criteria are proposed from AS/NZS 4130 and DTL practice. SBR to elect its witness/hold points in the “SBR” column before the plan is issued for construction.
DTL (WA) Pty Ltd · 2/28 Horus Bend, Bibra Lake WA 6163 · ABN 45 677 646 454 · Commercial-in-Confidence
DTL (WA) Pty Ltd · Commercial-in-ConfidenceContract SBS10627 · PO 182113Page 1 of 4
HDPE Inspection & Test PlanBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-ITP-001
Rev A

1HDPE inspection & test points

H Hold — work stops until released W Witness — attend if elected R Record only REF section
No.ActivityAcceptance criteriaReferenceRecord DTL
H/W
SBR
H/W
Signed /
date
1.0Material receival & storageREF  
1.1Delivery inspectionPipe/fittings free of transit damage, gouges >10% wall, UV degradation.AS/NZS 4130Receival logH  
1.2Certification checkCoC & AS/NZS 4130 compliance certificate present; batch/heat recorded.SOW MDRTraceability recordH  
1.3StorageSupported, shaded, no point loads; UV protection if >12 months.Mfr guidanceW  
2.0Butt fusion jointingREF  
2.1Machine set-upCorrect clamps/inserts; faces aligned; drag pressure recorded.AS/NZS 4130 App.Weld registerW  
2.2Heater plate tempPlate temperature within approved range, verified each shift.TEM-0003Heater Plate CheckH  
2.3Fusion parametersHeat-soak, fusion & cooling times/pressures to approved parameters for size/class.TEM-0003Weld registerH  
2.4Bead inspectionTwin uniform beads, correct width, no mismatch >10% wall; cooled undisturbed.AS/NZS 4130Weld registerH  
2.5Weld numberingEach joint numbered and located on the weld map.QMP §5Weld mapR  
3.0InstallationREF  
3.1Stringing & alignmentRoute, bend radius ≥ mfr minimum, no kinks; support.DrawingITP sign-offW  
3.2Road crossings / coverDepth, sleeve/casing and cover to drawing.DrawingITP sign-offH  
3.3Earth moundingProfile and compaction to drawing.DrawingITP sign-offW  
4.0ConnectionsREF  
4.1Flanged / mechanical jointsAlignment, gasket, bolt torque to spec; connection recorded.Mfr specConnection recordH  
4.2ARV, tie-ins, standpipes, scourFit, orientation, function to drawing.DrawingITP sign-offW  
5.0Testing & handoverREF  
5.1Pressure / leak testTest pressure, hold time and acceptance to approved test procedure.AS/NZS 4130 / specTest certificateH  
5.2Weld map completeAll welds mapped and cross-referenced to the register.QMP §5Weld mapH  
5.3Records & MDRAll ITP points signed, NCRs closed, MDR compiled.SOW MDRMDRH  
DTL (WA) Pty Ltd · Commercial-in-ConfidenceContract SBS10627 · PO 182113Page 2 of 4
HDPE Inspection & Test PlanBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-ITP-001
Rev A

2How this ITP is used

SBR to complete the “SBR H/W” column at the QMP/ITP review, nominating which points it will hold or witness. DTL will re-issue the ITP as “Issued for Construction” once agreed.

Acceptance & sign-off

PREPARED — DTL
Tyson Knight
Director · Date
ACCEPTED — SBR
Principal Representative · Date
DTL (WA) Pty Ltd · Commercial-in-ConfidenceContract SBS10627 · PO 182113Page 3 of 4